Part-1 QC Notes of Electrical Inspector Part-1
Q1. |
What Article in NEC for photovoltaic
System? |
|
Answer : |
690 |
|
Q2. |
What Article for the NEC Alarm
System? |
|
Answer : |
760 |
|
Q3. |
Battery What Article in NEC? |
|
Answer : |
480 |
|
Q4. |
Fire pump motor operation what is the
distance from the Flooring? |
|
Answer : |
0 |
|
Q5. |
In Battery bank or Container what is
the minimum distance to the wall without manpower access? |
|
Answer : |
1 meter |
|
Q6. |
In combustible area a Switchgear top
of equipment to ceiling how much the minimum space distance? |
|
Answer : |
0 |
|
Q7. |
NEC Grounding Article? |
|
Answer : |
250 |
|
Q8. |
NEC Grounding for lightning
Protection? |
|
Answer : |
250.105 |
|
Q9. |
Lightning Protection System as per
UL? |
|
Answer : |
96 |
|
Q10. |
Circuit Computation in Room air
Conditioning? |
|
Answer : |
Room |
|
Q11. |
Grounding & bonding Duplex
receptacle connected to grounding equipment in hospital care? |
|
Answer : |
isolated ground |
|
Q12. |
Area of classification in hazardous
how to seal the conduit? All selection of the seal----- all of the above |
|
Answer : |
Room |
|
Q13. |
Emergency lighting during shut
down----------? Emergency transfer switch |
|
Answer : |
mergency transfer switch |
|
Q14. |
NEMA VE1 & Specification and NEMA VE --------------? |
|
Answer : |
standard used for design, manufacturing and testing of cable
tray |
|
Q15. |
Grounding & bonding Conductor
shall be suitable in wet corresive enviroment? Selection? Listed labeled mark |
|
Answer : |
yes |
|
Q16. |
In material, I RPM, VOLTAGE, IN MOTOR
the identification of this is? Name Plate- Selection: listed labled mark. |
|
Answer : |
name plate |
|
Q17. |
DUCT BANK CONDUIT as per NEMA RN? |
|
Answer : |
1 |
|
Q18. |
Minimum Conduit size in Saudi Aramco? |
|
Answer : |
3/4" |
|
Q19. |
Cable Tray modification, Cable Tray
to be made by continues grounding in the equipment |
|
Answer : |
TRUE / FALSE |
|
Q20. |
CONCELLED KNOBE & TUBING
WIRING--------------CONDUCTOR? |
|
Answer : |
6mm (1/4) |
|
Q21. |
NOISE SOCEPTIBILITY LEVEL? TO BE FAMILIAR |
|
Answer : |
NSL |
|
Q22. |
Wiring table in firepans If there is
what article & table? |
|
Answer : |
? |
|
Q23. |
Wiring table what article and table? |
|
Answer : |
310 |
|
Q24. |
What type of the cable used inside
the control panelof fire pumps? NM CABLE |
|
Answer : |
miniral insulated |
|
Q25. |
ILLUMINATION REQUIRED IN GENERAL AREA
LIGHTING? SELECTION 150, 200 |
|
Answer : |
200 |
|
Q26. |
What shall be provided in each Duct
where it terminates? |
|
Answer : |
end bell |
|
Q27. |
What are the conduit fittings in
Regid Conduit & LFMC? |
|
Answer : |
couplings and connector |
|
Q28. |
(4) & (5), If applicable How the
inspection will finalize during bolting----? Torquering |
|
Answer : |
0 |
|
Q29. |
Class 1. Division 2. In Class 1.
Division 2. locations, motors, generators, and other rotating electrical
machinery shall comply with (1), (2), or (3) |
|
Answer : |
Torquering |
|
Q30. |
Minimum ampere for Switch gear? |
|
Answer : |
2000 Ampere |
|
Q31. |
Max branch circuit in panel board? |
|
Answer : |
42 |
|
Q32. |
Enclosures installed in outdoor areas? |
|
Answer : |
NEMA type 3, 4 or 4X |
|
Q33. |
IEC 60529, NEMA type 4 4.) |
|
Answer : |
outdoor enclosure |
|
Q34. |
EMT can be used? |
|
Answer : |
Indoor non hazardous area |
|
Q35. |
Indoor nonhazardous area |
|
Answer : |
non -classified location |
|
Q36. |
Sacrificial anode? |
|
Answer : |
type of cathodic protection |
|
Q37. |
Magnesium |
|
Answer : |
galvanic anode |
|
Q38. |
Branch circuit conductor overload capacity?
125% |
|
Answer : |
1.25 |
|
Q39. |
Overhead line pipe crossing? SAES- B-064 |
|
Answer : |
SAES- B-064 |
|
Q40. |
Switch rack rated current? 600 A |
|
Answer : |
600 A |
- ARAMCO :: CBT QA/QC – Instrumentation Inspector Qualification Guideline
- Saudi Aramco Cbt Exam Questions and Answers
- CBT EXAM E-BOOKS
- QA/QC ELECTRICL Inspector Question & Answer Handbooks
- QA/QC E-books Category
- Electrical QC Notes of Saudi Aramco Qualification Guideline
- QAQC Questionnaires CONDUIT; CABLE TRAY; ENCLOSURES;
- INSTRUMENTATION QUESTIONAIRE: QAQC CBT ARAMCO
No comments:
Post a Comment